Construction site meeting minutes template

For progress meetings and site walks: safety first, then progress against the programme, what was decided, what is still open, and who does what before the next visit.

The template

Copy it, or download it and fill it in by hand.

Site meeting minutes

Issue the minutes to everyone present and to anyone named in an action. Unchallenged minutes are often taken as the agreed record.

ProjectName and number.
MeetingProgress meeting, site walk or coordination meeting.
Date and time
LocationSite address or the area walked.
WeatherIt matters for pours and roofing.
Chaired by
PresentName, company and role.

Safety

Incidents and near misses since the last meeting.

Toolbox talk topic and open safety actions.

Progress against programme

Area or tradePlannedActualNotes
Level, zone or trade.Where the programme says it should be.Where it is.Reason for any gap.

Decisions

DecisionAgreed byReference
One sentence each.Name and company.Time in the recording, drawing or instruction number.

Issues and RFIs

RefIssueOwnerNeeded by
RFI number.The question or problem.Who answers it.The date work stops without it.

Actions

ActionOwnerDue
Starts with a verb.One person.Before the next visit, ideally.

Next meeting

Date, time and place

The same template, filled in by Velkri

A 30-minute site walk, recorded on a phone

RRiverside Clinic renovationA 30-minute site walk, recorded on a phoneFilled by Velkri
Project
Riverside Clinic renovation
Meeting
Site walk, Level 2
Date and time
28 Oct 2026, 08:00
Location
Level 2, east wing
Weather
Dry, 14°C
Chaired by
Ravi Menon (site manager)
Present
Ravi Menon, Lena Ortiz (architect), Tom Hale (M&E), Sara Quinn (client)

Safety

  • No incidents. One near miss: unsecured board at the east stair, fixed on the day.

Progress against programme

Area or tradePlannedActualNotes
L2 partitions100%90%East corridor this week
L2 first fix M&E80%80%On programme

Decisions

DecisionAgreed byReference
Level 2 doors: solid core, 30-minute fire ratingSara Quinn (client)Site walk, 06:12From: Site walk · 06:12
Slab pour moves to TuesdayRavi MenonSite walk, 14:40From: Site walk · 14:40

Issues and RFIs

RefIssueOwnerNeeded by
RFI-031Door supplier lead time for fire-rated setsLena Ortiz4 NovFrom: Site walk · 09:30

Actions

ActionOwnerDue
Order Level 2 door setsTom Hale31 OctFrom: Site walk · 07:05
Confirm pump booking for TuesdayRavi Menon30 OctFrom: Site walk · 15:10

Next meeting

Date, time and place
4 Nov 2026, 08:00, site office

Confirmed by Ravi Menon

Ravi recorded the walk on his phone. Velkri wrote it up in this format, proposed the decisions and actions, and every reference opens the recording at that moment.

How to use it

Four habits that make it work.

  1. 1

    Start with safety

    Incidents, near misses and open safety actions come first, every time, so they are never squeezed out by programme talk.

  2. 2

    Check progress against the programme

    Planned against actual for each area or trade, with a reason for every gap.

  3. 3

    Record decisions with a reference

    Who agreed, from which company, and a reference you can point to later: a drawing, an instruction number, or the moment in a recording.

  4. 4

    Issue before the next shift

    Send the minutes to everyone present and everyone named in an action, and ask for corrections within a set time.

What should construction site meeting minutes include?

The project and meeting details, who was present (with company and role), safety, progress against the programme, decisions, issues and RFIs, and actions with owners and dates.

Can I record a site walk?

Yes, with everyone’s agreement. In Velkri you record on a phone and can add other phones as extra mics; the write-up follows the same format, with each decision linked to its moment.

Who should receive site meeting minutes?

Everyone who attended, everyone named in an action, and the client or their representative. Many contracts set a time limit for raising corrections.